Overview

Service Name

Final Building Permit

Final Building Permit

Description This service enables the customer to obtain a Building Permit for the project and start construction work (as per the permit title).

Details

Requester Contractor
Service Deliverables Final Building Permit
Service Request Channels Online
Service Hours Online: 24/7
Estimated Time to Deliver 2 Working Days
Service Fees
  • Normal Submission: AED 1.00 per ft2 on Total Built-Up-Area (minimum AED 200). The final building permit fees will be calculated after deducting the fees which were paid previously for the Interim & Preliminary Permit except for Mobilization and Excavation Permits.
  • For Industrial plot: the above fees not to exceed AED 250,000
  • Renewal of Final Building Permit: (AED 0.03 per ft2 on Total Built-Up-Area) x (No. of months requested for renewal) (Maximum AED 6,000 per month)
An additional fee of AED 10 as “Knowledge Dirham” and AED 10 as “Innovation Dirham” is applicable per transaction
Required Documents
Notes
  • The approved permit is valid for 4 years
  • Land Demarcation Certificate to be obtained before starting any activity at site